Originals in proposal

1.       Update all eddy covariance data from 2008-present using TOVI

                   

1/31/2022

2.       Upload all preliminary processed data to Ameriflux Network for QA/QC

04/15/2022* Goal is for preliminary data to be online searchable before the renewal is due.

3.       Identify, organize, and upload all ancillary data recommended by Ameriflux to link with flux data

08/31/2022

4.       Collate all flux and ancillary data for final submission to Ameriflux

10/31/2022

5.       Work with Ameriflux personnel to identify any additional changes/errors before data is fully online

11/30/2022

Actual Process

The original proposal and the actual process are quite different as the project goes on. CABBI team mainly lead by Bethany proposed the modified direction of how the pipeline needs to go. The NCSA team tried to implement the main objective of CABBI team. 

...

The code for the main pipeline

the code will be present in in github 

there are several prerequisite datasets to run the pipeline.

Convenience component

there are couple user friendly tool designed to help the user

...