GLTG: Submitted bugfix to get builds deploying, updated explore map popups to use the bin endpoint resulting in much faster load times, deployed the featured watershed accordion. All priority issues are complete for this release, and I'm moving onto issues with "Normal" priority. Also on track for release 1.1 by June 26th.
SeaGrant: Met and reviewed all proposed work for next release and added time estimates for my tasks in Sea Grant 2.1. Time estimates appear to be appropriate for my 10% allocation to the project.
NIST - conf. calls, review pull requests, cleanup git repo of extraneous projects, get more info about tornado scenario event, bug fixing
CyberSEES - GI Venture webinar, see where I can assist on birds eye view app
MSR - help Tingting with workflow for web app
NIST - conference calls for NIST tasks effecting software development, reviewed several pull requests, fixed bugs with the charting and log view. Started working on NISTCORE branding plugin and setting up the NISTCORE git repository
CyberSEES - attended GI Venture webinar covering papers and software updates, need to check with Jong to see if there has been much progress besides choosing to move forward with the mockup Brian created
MSR - responded to emails from Tingting who is trying to execute an NLDAS2 script on the rapid VM, but is running into issues with missing software packages
use cases section-- need to co-ordinate with Co PIs
Elasticity
Clients
Work with Kenton for other sections editing
IEEE Big Data Paper
Reviewed previous years paper in the same conference, discussed with Kenton about the type and format and decided on giving less emphasis on use cases, so no need to co-ordinate with use case PIs at this point. Also decided to take picture of our own so that GI,EXIF, opencv and ocr extractors can run on it and show the metadata that as an example in the paper.
Elasicity (In Progress) - Based on Rui's reports, compiled the first version of the section, did some literature survey for the context of our work, why one would use our module over other existing solution and for future direction, designing some experiments for the paper and SC Poster. Planning on doing the experiments next week.
Started to co-ordinate with Greg for his work for the paper
CZ use case meeting with students and Prof. Praveen. It is decided to give priority to the development of DTS service for landsat data and Qina's usecase for the summer. Another meeting with Qina is required.