Who | Planned - Monday | Accomplished - Friday |
---|
|
|
|
|
| industry: rokwire: - update travis-ci yml
- PR on events building block
- discussion and guidance on events manager
|
|
|
|
Caiting Wu | - Install Elasticsearch and Kibana and get both running on local machine
- Familiarize with both tools and experiment indexing with Elasticsearch
- Familiarize with using cURL, REST API and JSON format
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| Rokwire | Rokwire |
|
|
|
|
|
|
|
|
|
| - OSN report
- EarthCube
- Clowder All Paws prep
- Clowder Video brainstorming
- NASA writeup
- HR
| - OSN report
- EarthCube
- Clowder All Paws prep
- Clowder Video brainstroming
- NASA writeup
- HR
|
| - Industry planning
- Clowder PRs and new features
- SMU deep Learning
- BD CZO use case
- OOO Friday
| - Industry planning
- Clowder PRs and new features
- SMU deep Learning
- BD CZO use case
- OOO Friday
|
|
|
|
| - purge canopycover from betyDB and upload revised values
- script for marking FLIR 2017 datasets as error w/ YAML file (ideally reuse for archive tagging)
- EnvironmentLogger sample data copy
- Elasticsearch indexing for TERRA
- SYN - clowder archiving support PR round II w extractor architecture
| - new canopy cover values uploaded to bety
- script for FLIR 2017 datasets done, needed permissions to write to protected directories
- EnvironmentLogger netCDF files copied over
- Clowder design work for extractor-based archiving
- wrote new GDAL dockerfile with latest version for geoTIFF header modifications
|
| INCORE Farmdoc - continue with the database
 - SQL queries
- parse data from the Matlab file

MDF - continue with MaterialIO
- continue with another dataset
| INCORE Farmdoc - design tweaked, VM test
- part done
- done
|
| - CHEESE / NDS
- Meeting Thursday to touch base
- Industry
- Help as needed with AWS setup
- Help plan next steps in Clowder un/archival (AWS Glacier?)
- Update previous PR to prevent navigation when clicking Reset
- WholeTale
- Further discussion about notification-stream UX improvements
- UI/UX meeting this week
|
|
| - GLTG
 - In Review:
- IMLCZO
- Re-run Parsers for Flux Tower and Allerton non-Decagon
  - In Review:
- Pull Requests
- VSL
| - GLTG
- IMLCZO
- Re-ran Parsers for Flux Tower and Allerton non-Decagon

|
|
|
|
|
|
|
| - F/U w/ Finance on HRTs, Agreements (MDF,FD)
- PEARC/CSSI Meeting plannning
- GLTG - June/Aug Milestones
- In-Core Milestones - needs work
- In-Core Web Page Planning
- Farm Doc - release planning
- BD - TOS NARA Follow up still
- Attempting Meeting Updates to Zoom?
- ITIL Presentation ... - not started
| - MDF agreement still not back and FD still not signed
- HRTs and VSLs followed up on
- PEARC/CSSI - break contract signed
- GLTG - planning milestones sent to Moira
- Incore web planning page draft done
- Farm-Doc release planning done - need to see if it is ready to transfer to tasks
- TOS - hopefully will get to me middle of next week
- Zoom updates - I think I have a plan ... haven't started yet
|
|
|
|
| - Finalize setting up incore service kubernetes
- Working on using restful service for profile building block
- Finalize dockerizing profile building block
| - Finished automating incore service kubernetes in both dev and prod
- Separated pii and non-pii in separated database
- Dockerized profiles rest service
|