WhoMonday - PlannedFriday - Accomplished
Brock Angelo  
Edgar F. Black 
  • MSC
    • MSC web application is back on line. Thanks to Luigi and Rob for finding the problem
    • MSC web application features are complete. It was missing the feature of allow analysis with a limited number of data points. Thanks to Yan for the modification.
    • AJT first draft paper is still undergoing changes. Questions were sent to researchers. Waiting for feedback.
Rob Kooper
  • PEcAn
    • qsub
    • misc bug fixes towards release
  • SEAD
    • speed of clowder
  • BD
    • more docker stuff
  • PEcAn
    • misc bug fixes
  • SEAD
    • found missing index
  • BD
    • helped Luigi with download files
Jong Lee
  • CyberSEES report
  • Riverside Research meeting
 
Rui Liu
  • BD: Continue implementing docker elasticity integration.
  • Earthcube: work on Semantic Annotation Service.
  • BD: BD-703: finished start and remove docker containers, partly finished resuming suspended docker machines.
  • Earthcube: SAS variable name annotation. 2 tasks:
    • Endpoint implementation (ECGS-26): done.
    • GUI (ECGS-54): started working on it.
Kenton McHenry
  • Brown Dog landing pages
  • BD web page updates
  • Refresh BD slides for upcoming presentations
  • BD web page updates
  • Re-org stuff
Luigi Marini
  • BD:
    • sign up form using brown dog
    • openid example using crowd id
    • oauth2 testing using existing providers
  • SEAD 
    • staging area pull requests
    • GUI clean up
    • user tests feedback
  • Clowder documentation
  • XSEDE VAT multimedia search bug and speed ups
  • Earthcube JSON-LD finishing touches - remove old metadata endpoints
  • GLTG: Zip download of large files in Clowder
  • BD: Setup opensource browndog directory and got php script to work, need to finish form
  • SEAD: Staging area 3 finish
  • IMLCZO: Meetings and slides in preparation of NSF Review Oct. 14
  • Earthcube planning meetings
Christopher Navarro
  • NIST - final preparations for Ergo training (slides, topics, etc)
  • BrownDog - technical meeting, continue working on creating datawolf workflow from polyglot log file
  • NIST - prepared user tutorial slides and ergo build, tested ergo build, developer notes for developer sessions, meeting to discuss utility network data for NIST-Core
Michal Ondrejcek
  1. Finish the Station merge with CSS, JavaScript MWRD-158
  2. Finish data ingestion design for Stations, MWRD-114
  3. Finish documentation for Stations, MWRD-114
  4. Continue with general Documentation
  1. DONE
  2. the POST does not work properly. http works, AJAX doesn't, GET works, need help
  3. DONE
  4. Almost done, send next week
Smruti Padhy
  • BD- finish landsat extractor
  • SDN - Add weights to the network graph and test the implemenation
  • Tuesday - Friday Vacation
  • BD
    • zip/unzip of input files for landsat extractor done.
    • Hotel Reservation for IEEE Big Data 2015
  • SDN - Added weights to the network graph and tested the implementation. Still need to fix some issue on path lengths
  • Tuesday- Friday Vacation
Sandeep Puthanveetil Satheesan
  • BD
    • Complete and send the write-up about HPC support for extractors to the team
  • VAT
    • Complete fixing the issue with multimedia search
  • DEBOD
    • Set up some of the extractors available (census and handwritten digits)
    • Decide upon the data organization and add files to Clowder accordingly
  • BD
    • Completed the write-up.
  • VAT
    • Completed fixing the issue with multimedia search with the help of Luigi Marini
  • DEBOD
    • Started testing existing handwritten digit extractors using DEBOD data
    • Completed testing KNN-Digit extractor

Inna ZharnitskyBrown Dog tool catalog - continue working on assigned tasks.BD Tools Catalog - change level of tool when interface level is changed. Interface can be edited, file added/removed, admin can approve/revoke the interface - all these operations change the status of the interface. Since the level of the tool is the highest level of its published interface, every time interface status changed, need to update level of corresponding tool.
Marcus Slavenas
  • BD
    • tool-catalog - interface for upload multiple files
  • IARP
    • determine which classifier to work on next and proceed
  • GLTG
    • Test/run on dev USGS addition of new measurements
    • Check/fix noaa data not working on production site
  • BD
    • tools-catalog
      • added uploading multiple files to interface
        • added metadata field for file type (source, docker, input, output), but still needs to be assigned correct value
        • views still need a lot clean up
    • handwriting extractor - edited for pull request, removed medici-key and added inputting uname/pword for basic authentication
  • IARP
    • improve kill punch/border extractor - add derived images to dataset
    • get mean grey and kill punch border extractors running on iarp server
Indira Gutierrez Polo
  • CyberSEES: Continue working of refactoring on the page.
  • SEAD
    • Finish Matchmaker
    • Add retract submission functionality for curation objects.
  • CyberSEES: Continue working of refactoring on the page.
  • SEAD
    • Finish Matchmaker
    • Add retract submission functionality for curation objects.
    • List curation objects associated with a dataset in the dataset page
    • Fix color tags in the file page.
    • Updated post to the repository for latest shim requirements.
Jason Votava
  • BD
    • Sprint task updates
  • NIST
    • Set next development goal (Private auth spec? Something flashy?)
  • GLTG
    • Coordinate discussion with CS team
    • Get next usability feature planned
  • MWRD
    • Review final draft of written materials/deliver them
  • NCSA
    • Submit final draft of trip report
    • Hotel plans for NDS
  • BD
    • Agile board updated
  • NIST
    • Greece prep complete
    • Budget adjustment justification submitted
  • GLTG
    • Contacting students in CS department for additional info
    • Prep for demo on Oct 14
  • MWRD
    • Waiting on materials. Due Monday
    • Coordinate parking pass for Chicago onsite training session
  • NCSA
    • Trip report submitted
    • NDS hotel confirmed
Yong Wook Kim
  • Create network discretization unit selector
  • Create JMap mouse action (zoom in, out, selection, pan)
  • Modify Scenario Earthquake map picker as JMap
  • Fix scenario Earthquake map picker
  • Create Tornado start and end point map picker
  • Created network discretization unit selector
  • Created JMap mouse actions
  • Modified Scenario Earthquake map picker as JMap
  • Fixed scenario Earthquake map picker
  • Working on Tornado start and end point map picker
Omar Elabd
  • RDF
  • Tweaks to Roadways
  • Merged roadways branch with develop, Submitted pull request.
  • RDF reading
Yan Zhao