When: July 18th

Where

Action Plan :

(June 6th  - June 24th ) - 3 weeks for development/ environment setup , (Development and Environment setup preparation

June 27th - 1st July ) for fine -   Fine tuning/deployment, (

2nd July- 8th July ) for testing -  Testing

11th July, 12th July - Demo to ISDA group.