Clip chart data based on selected dates

XMLWordPrintableJSON

    • Icon: Task Task
    • Resolution: Fixed
    • Icon: Normal Normal
    • 0.1
    • None
    • None
    • None
    • CCROP Sprint 1, CCROP Sprint 4, CCROP Sprint 5, CCROP Sprint 6

      If the user selects establishment and termination dates, clip the output of charts accordingly. 

              sandeeps Sandeep Puthanveetil Satheesan
              sandeeps Sandeep Puthanveetil Satheesan
              Votes:
              0 Vote for this issue
              Watchers:
              1 Start watching this issue

                Created:
                Updated:
                Resolved:

                  Estimated:
                  Original Estimate - 4 hours Original Estimate - 4 hours
                  4h
                  Remaining:
                  Remaining Estimate - 0 minutes
                  0m
                  Logged:
                  Time Spent - 6 hours