The following are known and planned activities/projects. We have committed resources to these projects are either 1) defining requirements/tasks in the backlog or 2) actively working on requirements/task in sprint. In other words, there should be tasks in JIRA for these projects now to meet the deadline.

ActivityTimeframeStatusDeliverables
iSchool pilot support4/1 ~ 6/15/2017

Post Development

Active support

JIRA Tasks
PI4 Bootcamp5/30-6/9/17Active support
BioCADDIE pilot5/1 - 7/30/2017Active DevelopmentJIRA Tasks
Earth Cube All-Hands meeting6/8/2017Active DevelopmentJIRA Tasks
ThinkChicago8/2 - 8/4/2017Active DevelopmentJIRA Tasks
Container workshop8/14 - 8/16/2017In PlanningUndefined
National Bridge InventoryTBDDiscussing


The following are anticipated projects and priorities. No resources are actively committed to working on either requirements or tasks. In other words, there are no tasks in JIRA.

ActivityTimeframeStatusDeliverables
DataDNS?DiscussingUndefined
ESIP Meeting7/25 - 7/28

Undefined

NCSA Industry PartnersJune 20-21DiscussingUndefined
NDSC8October 2017Undefined
SC17 Demo11/12 - 11/17/2017Undefined

The following are Labs Workbench planned features. This is what we've prioritized to work on outside of the above deadlines.

  • Failover/backups
  • Deploy-tools replacement/packaging for install
  • Commercial cloud support/storage generalization
  • Improved scaling/minimal cluster configuration – migration path from single node to multinode?
  • Security analysis for Docker containers
  • Oauth support
  • Project-specific catalogs and views